KILTER POWER
How It Works

We measure first. Equipment comes after.

Every recommendation rests on data from your own electrical system, gathered before anything is installed and again after.

  1. Evaluation
    1. 1

      First conversation

      We review your utility bills and one-line diagram, and ask about your transformers, switchgear, motors, drives, HVAC, compressors and maintenance history.

    2. 2

      Engineering site survey

      An engineer walks your electrical rooms, checks panels, grounding, capacitor banks and filters, and talks to the people who maintain the equipment.

    3. 3

      Power-quality measurement

      Temporary meters record voltage, current, kW, kVA, kVAR, power factor, voltage and current harmonics, demand, imbalance and transients. The data defines the problem.

    4. 4

      Engineering report

      Current operating conditions, root causes, what they cost you, maintenance concerns and the equipment at risk, with recommendations.

    5. 5

      Recommendation

      Panel-level correction with Reinigen, facility-wide correction with MPTS, or other fixes where they fit better: grounding, load balancing, filters, metering or maintenance.

  2. Installation
    1. 6

      Installation

      Your own licensed electrician installs the recommended equipment, to the National Electrical Code and local code. For MPTS, a monitoring meter goes in first and its data sizes the units. The same measurements run, so before and after are compared on your own system.

    2. 7

      Performance report

      Measured changes in power factor, current, kVA, kVAR, demand, energy and harmonics, with payback and released capacity.

  3. Verification
    1. 8

      Ongoing verification

      Measurement after installation, and yearly if you want it, so the result stays documented and holds up in front of your finance team. Then expand to more panels or buildings, or act on the other recommendations.

The Physics, Briefly

Why less current is the whole point.

Power factor, as a beer

The beer is the work you use. The foam does no work, but the utility still has to fill the whole mug, and your wires still have to carry it. Drag the slider, or pick a reading from the measured case.

115 kVA

delivered to get 100 kW of work done

Beer: the work
100 kW
Foam: does no work
15 kVA
The mug to fill
115 kVA

At 0.87, 13% of everything the wires carry is foam. It fills the transformer and heats the cables, and some US utilities bill for it.

Drawn to scale for 100 kW of work: the foam is the extra kVA the wires carry (kVA − kW). The presets are the measured case’s average and lowest readings before correction, and its average after.

S² = P² + Q²

Apparent power (S, kVA) combines real power (P, kW), which does the work, with reactive power (Q, kVAR), which does not. Cut Q and S falls at the same real load, and with it the current.

PF = P ÷ S

Power factor is the share of apparent power doing real work. At 0.87, a panel carries about 15% more current than the same load would need at 1.00.

Loss = I²R

Losses in conductors and transformers grow with the square of current, so a 10% cut in current trims those losses by about 19%.

5th · 7th · 11th

Drives, LED drivers and switch-mode power supplies draw current in pulses. The pulses add harmonic currents that raise RMS current, heat neutrals and transformers, and travel to equipment elsewhere on the same network.

The power triangle at one switchboard

φPQSS after
P, real power
175 kW
Q, reactive power
101 kVAR
S, apparent power before
203 kVA
S after correction
about 175 kVA
Average readings at the distribution facility’s main switchboard before correction: 175 kW of real load needed 203 kVA, because 101 kVAR of reactive power rode along. With the reactive power corrected, the same 175 kW would need about 175 kVA, some 14% less.
Draw your own triangle: Power Factor Check